The following schedule of events are for the replacement of the roof and windows, provided by the Property & Technology Committee:
Roof
- 9/22 – Truck of insulation delivered to NW corner of the south parking lot.
- 9/26 – Installation begins. Pull off the rock and store on the parking lot next to the insulation.
- 9/28-10/7 – Tear off the old roof and install the new roof.
- 10/8-10/14 – Depending on weather, finish and clean up.
Windows
- 9/22-23 – Measure and order the new windows (8 weeks to build our new windows).
- 11/21 – Installation of the new windows.