Roof & Window Update

Roof & Window Update

The following schedule of events are for the replacement of the roof and windows, provided by the Property & Technology Committee:

Roof

  • 9/22 – Truck of insulation delivered to NW corner of the south parking lot.
  • 9/26 – Installation begins. Pull off the rock and store on the parking lot next to the insulation.
  • 9/28-10/7 – Tear off the old roof and install the new roof.
  • 10/8-10/14 – Depending on weather, finish and clean up.

Windows

  • 9/22-23 – Measure and order the new windows (8 weeks to build our new windows).
  • 11/21 – Installation of the new windows.